Projected Building Cost as of May 10, 2011 Constituency Meeting Vote

Design & Engineering Costs $   300,000.00  
Building Costs 5,200,000.00 May 10 Vote
TOTAL Projected Cost 5,500,000.00  
Playfield - Lower - ETC

   250,000.00

ADDL. 
TOTAL Cash Raised 2,229,778.19
07/20/11
TOTAL Interest Paid @ 6% to NPUC     48,660.39 07/11/11
Total Principle Repaid to NPUC 17,673.16 07/11/11

LCAS Building Progress

  • NEW PHOTO ALBUM AVAILABLE with hundreds of pictures. http://lcasnewschool.shutterfly.com
  • PRAISE THE LORD - WE SURPASSED OUR GOAL FOR MAY 31, 2010
  • LCAS the "Old School" was burned 6/27/2010.
  • Ground was officially "broken" - July 11, 2010 -$3.8 million estimated cost above $300,000Construction has begun - Pray for safety, continued progress.
  • Footings formed - .
  • Parking area revision - Road Soil unstable
  • Fantastic Turnout for Workbee  8/1/2010 - ReBar for Footings DONE! THANK YOU!
  •  Workbee - August 29.2010  Tied Rebar for floors- Lay Brick - Great Start! Thanks
  • Workbee - September 12, 2010 - more brick & framing  Thank you for your help.
  • Festival of Progress - Phase II - October 17, 2010
  • Phase II = 1.5 million by December 31, 2011 - Pledges by May 31, 2011 
  • Unstable soil in front of building removed and hillside stabilized with rock and redesign of the parking lot.  (2 levels)
  • Roof in progress - Structure covered - November 12, 2010
  • NEEDED - $750,000 in cash by May 31, 2011 to stay within approved loan amount
  • 12/7/10 - LCAS Building Committee Budgeted 4.6 million for total cost after 300K for design.
  • Roof is on.  Praise the Lord for progress.
  • $183,482 of the $750,000 needed by May 31.2011 24.5% of goal (2/20/2011)
  • Feb 6, 2011 - Clean-up WorkBee - Many hands made lite work - Great Turnout. 
  • May 10 - LCAS Constituency Meeting -  Approved 5.2 million budget   for Building cost -
  • Approved the repair and lowering of the playfield to the level of the new school about 4'.  With the stipulation that this is to be done as a separate project above the 5.2 million construction Cost.  Construction has made playfield unusable. 
  • $319,594.56 was raised toward the 750,000 in cash needed by May 31.  (5/29/11)
  • July 18 - Trees being removed from behind the trailer that is being used for heated dry storage for the school.  A tree was dropped through the east end of the trailer exposing the items inside to the weather. And the electricity no longer is available for the trailer
  • $ 449,769.44 given and pledged toward Phase II - 1,500,000 by 12/31/11  (7/24/11) (Pledges=$19,941.25)